Project Summary
Project Summary
Sector Name : HEALTH AND FAMILY WELFARE.
Agency Name : HOSPITAL SERVICES CONSULTANCY CORPORATION LTD.
Project Name : CONSTRUCTION OF HOSPITAL AND OPD BLOCK NCI JHAJJAR.

Reported Date : 07-JUL-23

Monthly Report : 6 / 2023

  

   

Total/Pending/Completed Milestone - 2 / 0 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
505.580586.96

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
586.9600586.96

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20180/04/2020

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks