Project Summary
Project Summary
Sector Name : HEALTH AND FAMILY WELFARE.
Agency Name : HOSPITAL SERVICES CONSULTANCY CORPORATION LTD.
Project Name : RESIDENTIAL COMPLEX AND OPD BLOCK, AIIMS, NAGPUR MAHARASTRA.

Reported Date : 07-JUL-23

Monthly Report : 6 / 2023

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
274.190274.19

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
259.4600259.46

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20190/01/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks