Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : MANSI-PURNIA (EXTENSION OF MANSI-SAHARSA) GAN ECR.

Reported Date : 08-MAR-22

Monthly Report : 2 / 2022

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
477.88751.55751.55

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
694.7328.13.26723.12

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20120/02/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
400

Ministry Review Date

LatestLastPhysical Progress (%)Status
95Completed

Monthly Status

Background Information

commissioned

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks