Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : PALWAL-BHUTESWAR 3RD LINE DOUBLING(NCR)(RVNL).

Reported Date : 21-AUG-13

Monthly Report : 6 / 2013

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
240380355

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
334.5900334.59

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/200911/20120/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1.540

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks