Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : METROPOLITAN RAPID TRANSPORT PROJECTS.
Project Name : EXTENSION OF MRTS FROM VELACHERY TO STN. THOMAS, MTP.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   98.05

Time Overrun (Months)-    143

Total/Pending/Completed Milestone - 4 / 1 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
495.74734.01981.83

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
623.019.320632.33

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20135/20255/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
.010

Ministry Review Date

LatestLastPhysical Progress (%)Status
98Ongoing

Monthly Status

Background Information

PSC Box Girder concrete stressing completed. Launching preliminary work in progress. P174A-Concreting work completed. De-shuttering & temporary staging removal work in progress. P157-Up lone PSC box girder launching preliminay work is in progress.Casting of girders in progress

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone