Sector Name : RAILWAYS.
Agency Name : METROPOLITAN RAPID TRANSPORT PROJECTS.
Project Name : EXTENSION OF MRTS FROM VELACHERY TO STN. THOMAS, MTP.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 4 / 1 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
734.01981.83981.83

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
632.3308.1640.43

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20248/20258/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
10

Ministry Review Date

LatestLastPhysical Progress (%)Status
98Ongoing

Monthly Status

Background Information

Railway Works have been completed. Commissioning will be done by August 2025 due to concurrent CMRL Works.Casting of girders in progress