Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : METROPOLITAN RAPID TRANSPORT PROJECTS.
Project Name : EXTENSION OF MRTS FROM VELACHERY TO STN. THOMAS, MTP.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   48.06

Time Overrun (Months)-    135

Total/Pending/Completed Milestone - 4 / 1 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
495.740734.01

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
565.7352.744.54623.01

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20136/20249/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
58.1971.01

Ministry Review Date

LatestLastPhysical Progress (%)Status
97Ongoing

Monthly Status

Background Information

Casting of girders in progressWorks are in progress. It is proposed to complete VLCY - STM stretch in a single phase. Work will be completed by July 2023 and commissioning will be done on 31.12.2023.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone