Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : GOELKERA-MANOHARPUR,(LD)(SER).

Reported Date : 14-JAN-19

Monthly Report : 11 / 2018

  

   

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
261.70388

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
363.0526.563.62393.23

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20060/012/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
536.53

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

With commissioning of Goelkera-Posotia 17.37 km in November 2018, project fully completed and commissioned and handed over to Railways for opertaions.