Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WORKSHOPS & PRODUCTION UNIT.
Project Name : CHHAPRA-SETTING UP OF WHEEL MANUFACTURING PLANT.

Reported Date : 20-APR-15

Monthly Report : 2 / 2015

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
470.091417.231417.23

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1011.09241.5301252.62

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/08/2014

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3150

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks