Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : PANSPURA-KHARAGPUR 3D LINE.

Reported Date : 21-AUG-13

Monthly Report : 6 / 2013

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
252.5529.23529.23

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
249.3600249.36

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/201011/201212/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
29.820

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks