Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : BHOPAL BINA 3D LINE DOUBLING.

Reported Date : 21-AUG-18

Monthly Report : 6 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
687.201065

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1030.242.451.081033.77

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20100/012/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
200

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Track linking completed. Commissioning of remaining section Bhopal-Nishatpur (2.12 km) commissioned in June 2018.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks