Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : TIDIVANAM-NAGARI (NL).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   523.05

Time Overrun (Months)-    24339

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
582.833631.343631.34

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
763.7363.116.57833.41

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/03/20283/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
153.28110

Ministry Review Date

LatestLastPhysical Progress (%)Status
14Ongoing

Monthly Status

Background Information

Land Acquisition is in progress 722.69 Ha completed out of 727.14 Ha and 627.22 Ha Handed over to Railways. Walajah Road - Ranipet section (6 Km) commissioned for Goods Traffic on 23.11.2020. The Walajah Road - Nagari NL portion is required on priority to ease the operations over AJJ - RU section. EPC tenders awarded and work in progress for Nagari – Podathurpettai and Walajah Road - Sholingur Town Sections. Both Sections are targeted for completion by Mar - 2026.Land Acquisition is in progress and are in various stages.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone