Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : TIDIVANAM-NAGARI (NL).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   523.05

Time Overrun (Months)-    24327

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
582.8303631.34

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
697.1767.44-.88763.73

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/012/20263/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
200125.06

Ministry Review Date

LatestLastPhysical Progress (%)Status
10Ongoing

Monthly Status

Background Information

Land Acquisition is in progress and are in various stages.LPS for 725.21 Ha submitted during June 2010. Total amount of Rs.577.15 Cr deposited. 266 Ha land received so far. Reg Vengunam Forest Land (3.179 Ha) of TN & Pullur West Forest Land (4.70 Ha) of AP, both stage I & II approval given by MoEF&CC and diversion of land completed. WJR - Ranipet section (6 Km) commissioned for Goods Traffic on 23.11.2020. The WJR- NG NL portion is required on priority to ease the operations over AJJ - RU section.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone