Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : NEW B.G. LINE FROM ARARIA TO GALGALIA (THAKURGUNG), NEFR.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   728.02

Time Overrun (Months)-    78

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
532.872132.034412.25

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2360.381061.48308.813730.67

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20190/09/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
01145.79

Ministry Review Date

LatestLastPhysical Progress (%)Status
87Ongoing

Monthly Status

Background Information

Land Acquisition (Hect.): (Scope=684.549/Physical progress=682.591)=99.71% Earth Work (lakh cum.): (Scope=187.94/Physical progress=187.94)=100% Formation (Km.): (Scope=111.037/Physical progress=111.037)=100% Major Bridge - Sub Strc. (Nos.): (Scope=64/Physical progress=64)=100% Major Bridge - Super Strc. (Nos.): (Scope=64/Physical progress=64)=100% Minor Bridge(Nos.): (Scope=153/Physical progress=153)=100% RUB (Nos.): (Scope=110/Physical progress=110)=100% Track Linking-Main Line (Km.): (Scope=111.252/Physical progress=100.12)=80% Station Building (Nos.): (Scope=14/Physical progress=12)=85.71%Land Acquisition (Hect.): (Scope=684.549/Physical progress=682.591)=99.47% Earth Work (lakh cum.): (Scope=187.94/Physical progress=155.10)=82.53% Formation (Km.): (Scope=111.037/Physical progress=49.095)=44.21% Major Bridge - Sub Strc. (Nos.): (Scope=30/Physical progress=30)=100% Major Bridge - Super Strc. (Nos.): (Scope=55/Physical progress=10)=18.18% Minor Bridge(Nos.): (Scope=118/Physical progress=98)=83.05% RUB (Nos.): (Scope=115/Physical progress=97)=84.35% Track Linking-Main Line (Km.): (Scope=121.237/Physical progress=30.842)=25.44% Station Building (Nos.): (Scope=14/Physical progress=2)=14.29%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone