Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : NEW B.G. LINE FROM ARARIA TO GALGALIA (THAKURGUNG), NEFR.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   397.31

Time Overrun (Months)-    69

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
532.872132.032650

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1472.74720.17167.472360.38

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20190/012/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
7000

Ministry Review Date

LatestLastPhysical Progress (%)Status
72.5Ongoing

Monthly Status

Background Information

Land Acquisition (Hect.): (Scope=684.549/Physical progress=682.591)=99.47% Earth Work (lakh cum.): (Scope=187.94/Physical progress=155.10)=82.53% Formation (Km.): (Scope=111.037/Physical progress=49.095)=44.21% Major Bridge - Sub Strc. (Nos.): (Scope=30/Physical progress=30)=100% Major Bridge - Super Strc. (Nos.): (Scope=55/Physical progress=10)=18.18% Minor Bridge(Nos.): (Scope=118/Physical progress=98)=83.05% RUB (Nos.): (Scope=115/Physical progress=97)=84.35% Track Linking-Main Line (Km.): (Scope=121.237/Physical progress=30.842)=25.44% Station Building (Nos.): (Scope=14/Physical progress=2)=14.29%Land Acquisition (Hect.): (Scope=684.549/Physical progress=673.951)=98.45% Earth Work (lakh cum.): (Scope=187.94/Physical progress=141.36)=75.22% Formation (Km.): (Scope=111.037/Physical progress=49.095)=44.21% Major Bridge - Sub Strc. (Nos.): (Scope=30/Physical progress=21)=70% Major Bridge - Super Strc. (Nos.): (Scope=55/Physical progress=6)=10.91% Minor Bridge(Nos.): (Scope=118/Physical progress=59)=50% RUB (Nos.): (Scope=115/Physical progress=75)=65.22% Station Building (Nos.): (Scope=14/Physical progress=2)=14.29%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone