Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTHERN RAILWAY.
Project Name : UTRATIA-ZAFRABAD, NR (LINE DOUBLING).

Reported Date : 13-AUG-19

Monthly Report : 6 / 2019

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
369.901581.53

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
886.073.531.64891.24

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20100/06/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
350

Ministry Review Date

LatestLastPhysical Progress (%)Status
18-JUL-1944Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks