Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : BARDHAMAN-KATWA (GC).

Reported Date : 07-OCT-21

Monthly Report : 9 / 2021

  

   

Total/Pending/Completed Milestone - 7 / 0 / 7

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1106.6201091.59

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
991.3910.581.811003.78

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20100/03/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
100

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Bardhman - Katwa work, has been commissioned on 30.12.2017. Subsequently the following material modification works were sanctioned :- 1. Katwa – Bazarsau (30.59 km) doubling - Work was sanctioned in 2011-12 and cost of the project is Rs 256.63 Crs. Section Tenya to Gangatikuri (13.25 Km) - Commissioned on 30th March’2019. Section: Katwa - Gangatikuri (10.36 Km.) – Commissioned on 17.05.2021. Balance section Tenya – Bazarsau (6.98 Km) – Targeted for commissioning in 2021-22 and work in progress. 2. Katwa - Manteswar (34.40 km) new line - Work was sanctioned in 2011-12 and cost of the project is Rs 256.20 cr.- Work could not be started due to non availability of land. However the work has been kept in abeyance by Railway Board, vide letter 2019/W- /Genl./Budget/1, dated 24.09.2019. 3. Negun-Mangalkot (8.60 km) new line - Work was sanctioned in 2011-12 and cost of the project is Rs 82.11 cr. - Work could not be started due to non availability of land. However the work has been kept in abeyance by Railway Board, vide letter 2019/W- I/Genl./Budget/1, dated 24.09.2019. 4. Manteswar - Memari (35.60 km) new line - Work was sanctioned in 2011-12 and cost of the project is Rs 251.50 cr. - Work could not be started due to non availability of land. However the work has been kept in abeyance by Railway Board, vide letter 2019/W- I/Genl. /Budget/1, dated 24.09.2019.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks