Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : AGARTALA SABROOM, NL, NEFR.

Reported Date : 13-AUG-19

Monthly Report : 6 / 2019

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
114203407

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3169.58153.531.13354.18

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20140/06/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Land Acquisition (Hect.):(Scope=885.472/Physical progress=885.472)=100% Earth Work (Lakh Cum.):(Scope=339.16/Physical progress=339.16)=100% Formation (Km.):(Scope=114.39/Physical progress=114.39)=100% Major Bridge - Sub Strc. (Nos.):(Scope=25/Physical progress=25)=100% Major Bridge - Super Strc. (Nos.):(Scope=25/Physical progress=25)=100% Minor Bridge (Nos.) :(Scope=242/Physical progress=242)=100% ROB (Nos.) :(Scope=66/Physical progress=66)=100% RUB (Nos.):(Scope=38/Physical progress=38)=100% LHS (Nos.):(Scope=37/Physical progress=37)=100% Tunnels (Rm):(Scope=689/Physical progress=689)=100% Track Linking - Main Line (Km.):(Scope=114.664/Physical progress=114.664)=100% Station Building (Nos.):(Scope=11/Physical progress=11)=100%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks