Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : BHAIRABI SAIRONG, NL, NEFR.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   259.52

Time Overrun (Months)-    136

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2393.475021.458605

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
6206.59899.7171.727178.02

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20140/07/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
9150

Ministry Review Date

LatestLastPhysical Progress (%)Status
92Ongoing

Monthly Status

Background Information

Land Acquisition (Hect.):(Total Scope=481.76Ha/Physical progress=479.65Ha)=99.56% Earth Work (Lakh Cum.):(Scope=366/Physical progress=361)=98.75% Formation (Km.):(Scope=24.433/Physical progress=16)=66% Major Bridge-Sub Strc.(Nos.):(Scope=55/Physical progress=55)Progress=100% Major Bridge-Super Strc.(Nos.):(Scope=55/Physical progress=35) Progress=82% Minor Bridge (Nos.):(Scope=87/Physical progress=85) Progress=97% ROB (Nos.):(Scope=5/Physical progress=5)=100.00% RUB (Nos.):(Scope=4/Physical progress=4)=100.00% Tunnels (Rm.):(Scope=12853/Physical progress=12794)=99.54% Cut & Cover (Rm)=(Scope=2923/Physical Progress=2819)=96.44% Tarck linking (Km) = Scope = 51.38/Physical Progress = 9.00) = 18% Station Building (Nos) Scope = 4/Physical Progress = 3 [work is in progress] (70%)Land Acquisition (Hect.):(Total Scope=481.76Ha/Physical progress=479.65Ha)=99.56% Earth Work (Lakh Cum.):(Scope=366/Physical progress=351.88)=96.14% Formation (Km.):(Scope=24.433/Physical progress=11.925)=48.81% Major Bridge-Sub Strc.(Nos.):(Scope=55/Physical progress=53)Progress=96% Major Bridge-Super Strc.(Nos.):(Scope=55/Physical progress=17) Progress=74% Minor Bridge (Nos.):(Scope=87/Physical progress=82) Progress=94% ROB (Nos.):(Scope=5/Physical progress=5)=100.00% RUB (Nos.):(Scope=4/Physical progress=3)=75.00% Tunnels (Rm.):(Scope=12853/Physical progress=12794)=99.54% Cut & Cover (Rm)=(Scope=2923/Physical Progress=2795)=96% Tarck linking (Km) = Scope = 51.38/Physical Progress = 0.00) = 0% Station Building (Nos) Scope = 4/Physical Progress = work is in progress (70%)

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone