Land Acquisition (Hect.):(Total Scope=481.76Ha/Physical progress=481.76Ha)=100%
Earth Work (Lakh Cum.):(Scope=366/Physical progress=366)=100%
Formation (Km.):(Scope=24.433/Physical progress=24.433)=100%
Major Bridge-Sub Strc.(Nos.):(Scope=55/Physical progress=55)Progress=100%
Major Bridge-Super Strc.(Nos.):(Scope=55/Physical progress=55) Progress=100%
Minor Bridge (Nos.):(Scope=89/Physical progress=89) Progress=100%
ROB (Nos.):(Scope=5/Physical progress=5)=100.00%
RUB (Nos.):(Scope=4/Physical progress=4)=100.00%
Tunnels (Rm.):(Scope=12853/Physical progress=12853)=100%
Cut & Cover (Rm)=(Scope=2923/Physical Progress=2923)=100%
Tarck linking (Km) = (Scope = 51.38/Physical Progress = 51.38) = 100%
Station Building (Nos) Scope = 4/Physical Progress = 4 = 100%
Sairang Station is ready for operation. Upgradation work is in progress. | Land Acquisition (Hect.):(Total Scope=481.76Ha/Physical progress=479.65Ha)=99.56%
Earth Work (Lakh Cum.):(Scope=366/Physical progress=361)=98.75%
Formation (Km.):(Scope=24.433/Physical progress=16)=66%
Major Bridge-Sub Strc.(Nos.):(Scope=55/Physical progress=55)Progress=100%
Major Bridge-Super Strc.(Nos.):(Scope=55/Physical progress=35) Progress=82%
Minor Bridge (Nos.):(Scope=87/Physical progress=85) Progress=97%
ROB (Nos.):(Scope=5/Physical progress=5)=100.00%
RUB (Nos.):(Scope=4/Physical progress=4)=100.00%
Tunnels (Rm.):(Scope=12853/Physical progress=12794)=99.54%
Cut & Cover (Rm)=(Scope=2923/Physical Progress=2819)=96.44%
Tarck linking (Km) = Scope = 51.38/Physical Progress = 9.00) = 18%
Station Building (Nos) Scope = 4/Physical Progress = 3 [work is in progress] (70%) |