Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : BHAIRABI SAIRONG, NL, NEFR.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
6527.455021.458213.72

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
7906.2942.6252.978001.88

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20250/06/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
309.990

Ministry Review Date

LatestLastPhysical Progress (%)Status
97Ongoing

Monthly Status

Background Information

Land Acquisition (Hect.):(Total Scope=481.76Ha/Physical progress=481.76Ha)=100% Earth Work (Lakh Cum.):(Scope=366/Physical progress=366)=100% Formation (Km.):(Scope=24.433/Physical progress=24.433)=100% Major Bridge-Sub Strc.(Nos.):(Scope=55/Physical progress=55)Progress=100% Major Bridge-Super Strc.(Nos.):(Scope=55/Physical progress=55) Progress=100% Minor Bridge (Nos.):(Scope=89/Physical progress=89) Progress=100% ROB (Nos.):(Scope=5/Physical progress=5)=100.00% RUB (Nos.):(Scope=4/Physical progress=4)=100.00% Tunnels (Rm.):(Scope=12853/Physical progress=12853)=100% Cut & Cover (Rm)=(Scope=2923/Physical Progress=2923)=100% Tarck linking (Km) = (Scope = 51.38/Physical Progress = 51.38) = 100% Station Building (Nos) Scope = 4/Physical Progress = 4 = 100% Sairang Station is ready for operation. Upgradation work is in progress. Land Acquisition (Hect.):(Total Scope=481.76Ha/Physical progress=479.65Ha)=99.56% Earth Work (Lakh Cum.):(Scope=366/Physical progress=361)=98.75% Formation (Km.):(Scope=24.433/Physical progress=16)=66% Major Bridge-Sub Strc.(Nos.):(Scope=55/Physical progress=55)Progress=100% Major Bridge-Super Strc.(Nos.):(Scope=55/Physical progress=35) Progress=82% Minor Bridge (Nos.):(Scope=87/Physical progress=85) Progress=97% ROB (Nos.):(Scope=5/Physical progress=5)=100.00% RUB (Nos.):(Scope=4/Physical progress=4)=100.00% Tunnels (Rm.):(Scope=12853/Physical progress=12794)=99.54% Cut & Cover (Rm)=(Scope=2923/Physical Progress=2819)=96.44% Tarck linking (Km) = Scope = 51.38/Physical Progress = 9.00) = 18% Station Building (Nos) Scope = 4/Physical Progress = 3 [work is in progress] (70%)

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks