(i) 146 m. Tunnel Mining achieved during the month of March,2025. Cumulative Tunnel Mining 37036 m. out of total 38641 m. is completed upto 31st March, 2025.
(ii) 1716 m. Tunnel Lining achieved during the month of March,2025. Cumulative Tunnel Lining 28646 m. is completed upto 31st March, 2025.
(iii) Mining of all the Adits is completed. 164.50 m Adit Lining achieved during the month of March, 2025. Cumulative Adit Mining 1670.0 m is completed upto 31st March, 2025.
(iv)Steel Fabrication work of 10714 MT out of 14518 MT completed up to 31st March, 2025.
(v)Erection and Launching of Superstructure work of 5324 MT out of 14518 MT completed up to 31st March, 2025.
(vi) 52 nos. out of 53 nos. Pier/Abutment cap and 54 nos. out of 54 no. pile cap have been completed upto up to 31st March, 2025.
(vii) Tunnel Lining in Six (6) Tunnels completed up to 31st March, 2025.
(vii) Tunnel Mining in Twelve (12) Tunnels completed up to 31st March, 2025.
(ix) Presently Mining in balance Two (2) Tunnels and Lining in balance Eight (8) Tunnels is under progress.
(x) 478 m BLT (Cum. 7796 m.) completed upto 31st March, 2025.
| |