Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : SEVOK RANGPO, NEFR.

Reported Date : 11-JAN-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 2 / 2024

Cost Overrun (%)-   488.06

Time Overrun (Months)-    96

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1339.4807876.92

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3290.96003290.96

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20150/012/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
25000

Ministry Review Date

LatestLastPhysical Progress (%)Status
39.8Ongoing

Monthly Status

Background Information

"""1032 m Tunnel Mining has been achieved during this month. Cumulative Tunnel Mining till 30th Sept., 2022 is 22229.0 m. 130 m Tunnel Lining has been done in Tunnel T14 in this month. Cumulative tunnel lining 395 m completed as on 30.09.2022. 174.5 m Adit mining has been achieved during this month. Cumulative tunnel Adit mining till 30th Sept, 2022 is 4732.1 m. 23 no (670 m) of Piles have been casted during this month. Cumulative piles casted till 30th Sept.,2022 is 636 nos (17725 m). 140 Cum earthwork in excavation has been done in yard (i.e Sivok )in the month of Sept.,2022. 30 Cum earthwork in filling has been done (in Sivok Yard) in this month. "

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone