Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH WESTERN RAILWAY.
Project Name : SADULPUR-BIKANER AND RATANGARH-DEGANA GAUGE CANVESSION (NWR).

Reported Date : 17-NOV-11

Monthly Report : 9 / 2011

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
643.360803.39

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
756.9329.93-.32786.54

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20110/03/2012

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1100

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks