Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH WESTERN RAILWAY.
Project Name : JAIPUR - RINGUS - CHURU AND SIKAR - LOHARU GUAGE CONVERSION (NWR).

Reported Date : 12-JUN-19

Monthly Report : 4 / 2019

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
653.1901116

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
854.81011.44862.17

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20145/20194/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
600

Ministry Review Date

LatestLastPhysical Progress (%)Status
17-MAY-19100Completed

Monthly Status

Background Information

(1)Sikar-Loharu (122.13 km) section Section commissioned on 01.9.2015. (2) Sikar- Churu (90.46 km) Section (i) Sikar-Fatehpur Shekhawati (47.06 km) :- Operation of passenger trains has been inaugurated by Hon’ble MR on 20.06.2017. (ii) Fatehpur Shekhawati- Churu (43.40 km):- Train services have been introduced in the section by Hon’bleMoSR on 09.12.2017. With this entire Sikar-Churu section commissioned. (3) Jaipur-Ringas-Sikar (107.45km) section (04 parts)- (i) Sikar-Palsana(27 km) section:- Commissioned on 27.01.2019. (ii) Palsana-Ringas (23 km) section:- Commissioned on 27.01.2019. (iii) Jaipur -Govindgarh –Ringas (57.45 km) section:- CRS done on 24-25.04.2019.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks