Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : TINPAHAR - SAHIBGANJ (ER).

Reported Date : 14-JAN-19

Monthly Report : 11 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
167.730182.56

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
232.974.541.02238.53

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20120/011/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
30

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Commissioned on 31.03.2016.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks