Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : DAKSHIN-BARASAL-LAKSHMIKANTAPUR.

Reported Date : 13-AUG-19

Monthly Report : 6 / 2019

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
259.510533.59

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
147.56.73.08148.37

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20120/06/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1.30

Ministry Review Date

LatestLastPhysical Progress (%)Status
40Completed

Monthly Status

Background Information

The main work is doubling of Dakshin Barasat – Lakshmikantapur doubling (19.68 KM) The work is sanctioned in 2009-10. The work completed and commissioned on 29.09.2016. Subsequently the following material modification works were sanctioned :- 1. Jaynagar – Raidighi (20 KM) New line - The work sanctioned in 2009-10 and cost of the project is Rs 140.46 cr. FLS completed 100.87 hectare of private land is required. Work could not be started due to non availability of land 2. Joynagar – Durgapur ( 32.0 Km. ) New line – The work sanctioned in 2011 - 12 and cost of the project is Rs 273.88 cr. FLS completed. Part Estimates for FLS & Soil Investigation sanctioned. FLS completed. Work could not be started due to non availability of land

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

   <