Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : RATLAM-MHOW-KHANDWA-AKOLA (GC).

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   9.26

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
5677.885677.86203.51

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4243.3128.0913.44284.8

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20272/20272/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1136.60

Ministry Review Date

LatestLastPhysical Progress (%)Status
80Ongoing

Monthly Status

Background Information

206.81 Kms - Commissioned (Dhoswas-Ratlam-Mhow, Sanawad-Nimarkheri, Nimarkheri-Khandwa bye pass cabin-Mathela & Khandwa bye pass cabin -Khandwa Jn (up to WR Limit). 5.40 km – Sanawad-Omakareshwar commissioned.5.51 km - Mhow- Patalpani commissioned. 5.6 km - Patalpani- Badiya on Dec.26. 60.5 Km - Badiya-Mukhtiyara on Feb.27. 20.7 Km - Muktiyara-Omakareshwar21on May26. 21.54 Km - Fatehabad - Ujjain on commissioned.TDC : 207.40 Kms - Commissioned (Dhoswas-Ratlam-Mhow, Sanawad-Nimarkheri, Nimarkheri-Khandwa bye pass cabin-Mathela & Khandwa bye pass cabin -Khandwa Jn (up to WR Limit) : 5.40 km -Mar.24/April-24 (Sanawad-Omakareshwar) One train system : 5.51 km - Jan.24/ April-24 (Mhow- Patalpani) One train system : 4.6 Km - Dec.25 (Patalpani- Badiya) : 60.5 Km - Feb.27 (Badiya-Mukhtiyara) : 20.7 Km - Feb.26 (Muktiyara - Omakareshwar) : 21.54 Km - Commissioned (Fatehabad - Ujjain) : 9.51 Km - Jan.24/Apr-24 [Rau - Mhow (Dr. Ambedkar Nagar)] Subject to completion of timely completion of land acquisition. Work is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone