Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : RATLAM-MHOW-KHANDWA-AKOLA (GC).

Reported Date : 09-AUG-21

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 9 / 2021

Cost Overrun (%)-   76.13

Time Overrun (Months)-    12

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3503.695839.026171.08

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2261.1654.3512.092327.6

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20223/20233/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3500

Ministry Review Date

LatestLastPhysical Progress (%)Status
47Ongoing

Monthly Status

Background Information

Total length - 472.64 km + 22.96 km ( Through material modification for Fatehabad-Chandravatiganj- Ujjain). Western railway- 298.64 km+ 22.96 km South central railway-174.00 km Railway wise progress is as under:- Western Railway :- Sections Commissioned- (i) Dhoswas- Ratlam- Indore-Rau-Mhow– 147.70 KM (ii) Nimarkhedi- Mathela - 45.61 Km. (iii) Sanawad-Nimarkhedi (11.6 Km)-CRS inspection done on 31.03.2021. (iv) Fathabad-Ujjain (22.96 Km) –CRS inspection done on 11.02.2021. Work in progress:- i) Khandwa Bye Pass cabin to Khandwa (5.00 Km) –Tender for balance work awarded. Work is under progress. ii) Rau-Mhow doubling (9.50 km ) – Tendering work in progress. iii) For section from Muktiyar balwada to Sanawad (26.10 KM) having grade 1:150, EPC Tender has been prepared and sent to HQ for approval. iv) The section Mhow – Mukhtiyar balwada (58.55 Km) , operating department have asked for revision of Grade 1:150 instead of 1:100. Vide letter No.93/W-I/GC/W/12/ RTM-MHOW-Part-5 dated 05.07.2021 Railway Board has accorded approval for change in ruling gradient from 1in100 to 1 in 150. v) FLS tender has been prepared for fixing the alignment as per the revised grade. The tender has been opened on dated 30.09.2021. South Central Railway:- 1.Akola-Akot (43.50 Km) - commissioned. 2.Akot-Amalakhurd (77.43 Km) - Alignment is passing through Melghat tiger Reserve. Detailed Estimate sanctioned for carrying out GC on same alignment. But Forest and wild life clearances not received from Forest department. Work not started. 3. Amalkhurd - Khandwa (54.50 Km). - Work in progress. The track is passing through Reserved forest from Km 644.80 to km.619.80 between Gurhi-Amalakhurd stations. Revised on line application for diversion of forest land of 21.446 HA is submitted to Forest department on 26.05.2021. TDC : March 2023. Total length - 472.64 km + 22.96 km ( Through material modification for Fatehabad-Chandravatiganj- Ujjain). Western railway- 298.64 km+ 22.96 km South central railway-174.00 km Railway wise progress is as under:- Western Railway :- Sections Commissioned- (i) Dhoswas- Ratlam- Indore-Rau-Mhow– 147.70 KM (ii) Nimarkhedi- Mathela - 45.61 Km Work in progress:- (i) Sanawad-Nimarkhedi (11.6 Km)- Earthwork, bridges, track linking, 2 round tamping completed. . TDC - MARCH - 2021 (ii)Fathabad-Ujjain (22.96 Km) – CRS inspection done on 11.02.2021. Work yet to be started:- Mhow- Sanawad (84.65 Km ) : Detailed estimate sanctioned by Railway Board vide letter No. 93/W-I/GC/W/12/RTM-MHOW-Part-5 Dtd 05.07.19. Total 208.9 Hect. Forest land and 58.131 Hect. revenue land needs to be acquired. Demand note of Rs 34.12 Cr for forest land and Rs 14.98 Cr for revenue land is received. Land acquisition is under process. South Central Railway:- 1.Akola-Akot (43.50 Km) - commissioned. 2.Akot-Amalakhurd (77.43 Km) - Alignment is passing through Melghat tiger Reserve. Detailed Estimate sanctioned for carrying out GC on same alignment. But Forest and wild life clearances not received from Forest department. Work not started. 3. Amalkhurd - Khandwa (54.50 Km). - Work in progress. Trees felling permission from forest department of M.P. state is in process where the alignment is passing through Forest area for a length of 9.61 Kms. TDC : March 2022

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone