Reported Date :
06-NOV-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
10
/
2024
|
Cost Overrun (%)- 381.26
|
Time Overrun (Months)-
174
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| Deshalpur-Mothala(34 Km) :
(a) Deshalpar- Sanosara (25.50 Km) : Engine trial was successfully done on 31.01.24 by CPM (C) II ADI in Deshalpur-Sanosara (25.5km). Work is in progress. CRS planned on 29.03.24.
(b) Sanosara - Kothara (30.1 Km) : Engine trial was successfully done on 16.02.24 between Sanosara to Kothara 30.1 km (km 54.30 to km 84.40). Minor works, eg. wall of Bridges etc balance. CRS is to be done. Work is in progress.
Kothara - Naliya (17.5 Km ) : Engine trial was successfully done on 06.03.24 by CAO/C-II ADI in Kothara to Naliya (17.5 km) (km 84.40 to km 101.90). Minor works, eg. wall of Bridges etc balance. CRS is to be done. Work is in progress.
Naliya-Vayor (24.65 Km New Line) : Land acquisition is in process. 20A Notification for all 14 villages was issued on 02.05.23, 09.05.23 & 02.08.23. JMS of all the villages have been completed in Dec.2023. State govt. is being chased to prepare para 104 and issue notification 20E. Tender will be invited after LAQ process is completed. On receipt of Land EPC tender to be invited. TDC : 25.50 Km - Engine Rolling done in Deshalpur-Sanosara
: 30.1 Km - Engine Rolling done in Sanosara - Kothara
: 17.5 Km - Engine Rolling done in Kothara - Naliya
: 24.65 Km. - Sep-26 (Naliya - Vayor) |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |