Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : BHUJ-NALIYA(GC) WITH EXTENSION FROM NALIYA TO VAYOR (WR).

Reported Date : 06-NOV-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 10 / 2024

Cost Overrun (%)-   381.26

Time Overrun (Months)-    174

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
318.241531.551531.55

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
547.52770.1201317.64

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20129/20269/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
35030

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Deshalpur-Mothala(34 Km) : (a) Deshalpar- Sanosara (25.50 Km) : Engine trial was successfully done on 31.01.24 by CPM (C) II ADI in Deshalpur-Sanosara (25.5km). Work is in progress. CRS planned on 29.03.24. (b) Sanosara - Kothara (30.1 Km) : Engine trial was successfully done on 16.02.24 between Sanosara to Kothara 30.1 km (km 54.30 to km 84.40). Minor works, eg. wall of Bridges etc balance. CRS is to be done. Work is in progress. Kothara - Naliya (17.5 Km ) : Engine trial was successfully done on 06.03.24 by CAO/C-II ADI in Kothara to Naliya (17.5 km) (km 84.40 to km 101.90). Minor works, eg. wall of Bridges etc balance. CRS is to be done. Work is in progress. Naliya-Vayor (24.65 Km New Line) : Land acquisition is in process. 20A Notification for all 14 villages was issued on 02.05.23, 09.05.23 & 02.08.23. JMS of all the villages have been completed in Dec.2023. State govt. is being chased to prepare para 104 and issue notification 20E. Tender will be invited after LAQ process is completed. On receipt of Land EPC tender to be invited. TDC : 25.50 Km - Engine Rolling done in Deshalpur-Sanosara : 30.1 Km - Engine Rolling done in Sanosara - Kothara : 17.5 Km - Engine Rolling done in Kothara - Naliya : 24.65 Km. - Sep-26 (Naliya - Vayor)

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone