Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : BHUJ-NALIYA(GC) WITH EXTENSION FROM NALIYA TO VAYOR (WR).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   381.26

Time Overrun (Months)-    146

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
318.241531.551531.55

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
143.84403.680547.52

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20125/20245/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3500

Ministry Review Date

LatestLastPhysical Progress (%)Status
85Ongoing

Monthly Status

Background Information

Deshalpur-Mothala(34 Km) : (a) Deshalpar- Sanosara (25.50 Km) : Engine trial was successfully done on 31.01.24 by CPM (C) II ADI in Deshalpur-Sanosara (25.5km). Work is in progress. CRS planned on 29.03.24. (b) Sanosara - Kothara (30.1 Km) : Engine trial was successfully done on 16.02.24 between Sanosara to Kothara 30.1 km (km 54.30 to km 84.40). Minor works, eg. wall of Bridges etc balance. CRS is to be done. Work is in progress. Kothara - Naliya (17.5 Km ) : Engine trial was successfully done on 06.03.24 by CAO/C-II ADI in Kothara to Naliya (17.5 km) (km 84.40 to km 101.90). Minor works, eg. wall of Bridges etc balance. CRS is to be done. Work is in progress. Naliya-Vayor (24.65 Km New Line) : Land acquisition is in process. 20A Notification for all 14 villages was issued on 02.05.23, 09.05.23 & 02.08.23. JMS of all the villages have been completed in Dec.2023. State govt. is being chased to prepare para 104 and issue notification 20E. Tender will be invited after LAQ process is completed. On receipt of Land EPC tender to be invited. TDC : 25.50 Km - Engine Rolling done in Deshalpur-Sanosara : 30.1 Km - Engine Rolling done in Sanosara - Kothara : 17.5 Km - Engine Rolling done in Kothara - Naliya : 24.65 Km. - Sep-26 (Naliya - Vayor) Section bet. Bhuj-Desalpur commissioned. Tender for earthwork in formation, minor bridges, linking etc. awarded on 11.08.2022. Tender for Major Bridge awarded on 26.10.2022 & building structures awarded on 30.12.2022. Tender for PSSA is awarded on 28.06.2023. Revised Estimate of Bhuj-Naliya GC project costing Rs.1086.43 cr. submitted to Railway boards on 21.10.2022 for sanction. Duly modification with all compliance RE costing Rs. 1095.12 Cr. pending with Railway Boards. DE for Naliya - Vayor New Line portion Rs.442.03 Cr. under sanction with Boards.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone