Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : NEW LINE FROM DIMAPUR TO ZUBZA(KOHIMA) NATIONAL PROJECT (NEFR).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   186.39

Time Overrun (Months)-    132

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2326.5266636663

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2237.66912.21110.473260.34

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20150/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
11000

Ministry Review Date

LatestLastPhysical Progress (%)Status
47Ongoing

Monthly Status

Background Information

Land Acquisition (Hect):(Scope:798.804 /Physical progress : 795.734)=99.61% Earthwork(Lakh cum): (Scope: 231.25/Physical progress: 203.32)= 87.92% Formation (Km): (Scope: 54.17/Physical progress: 31.550)= 58.24% Major Bridge – Sub Strc. (Nos): (Scope: 24/Physical progress: 14)=58.33% Major Bridge – Sup Strc. (Nos): Scope: 24/Physical progress: 11)=45.83% Minor Bridge – (Nos): (Scope: 156/Physical progress: 142)=91.02% ROB (Nos): (Scope: 6/Physical progress: 4)=66.66% RUB (Nos): (Scope: 15/Physical progress: 13)=86.66% LHS (Nos): (Scope: 14/Physical progress: 14)=100% Tunnels (Rm): (Scope: 30910/Physical progress: 8457) = 27.36% Cut & Cover (Rm): (Scope: 723/Physical progress: 178)=24.62% Ballast Supply (Th. Cum): (Scope: 127/Physical progress: 18)=14.17% Track Linking - Main Line (Km): (Scope: 82.5/Physical progress: 16.2)=19.64% Station Building (Nos.): (Scope: 8/Physical progress: 3)=37.5% Land Acquisition (Hect):(Scope:795.734 /Physical progress : 795.734)=100% Earthwork(Lakh cum): (Scope: 231.25/Physical progress: 202.20)= 87.43% Formation (Km): (Scope: 54.17/Physical progress: 29.39)= 54.25% Major Bridge – Sub Strc. (Nos): (Scope: 24/Physical progress: 12)=50% Major Bridge – Sup Strc. (Nos): Scope: 24/Physical progress: 9)=37.5% Minor Bridge – (Nos): (Scope: 156/Physical progress: 142)=91.02% ROB (Nos): (Scope: 6/Physical progress: 4)=66.66% RUB (Nos): (Scope: 15/Physical progress: 11)=73.33% LHS (Nos): (Scope: 14/Physical progress: 14)=100% Tunnels (Rm): (Scope: 30910/Physical progress: 6416) = 20.75% Cut & Cover (Rm): (Scope: 723/Physical progress: 185)=25.58% Ballast Supply (Th. Cum): (Scope: 127/Physical progress: 18)=14.17% Track Linking - Main Line (Km): (Scope: 82.5/Physical progress: 16.2)=19.64% Station Building (Nos.): (Scope: 8/Physical progress: 3)=37.5%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone