Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : NEW LINE FROM DIMAPUR TO ZUBZA(KOHIMA) NATIONAL PROJECT (NEFR).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   186.4

Time Overrun (Months)-    177

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2326.526663.26663.2

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3260.34989.87281.174531.38

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20150/012/2029

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
01135.21

Ministry Review Date

LatestLastPhysical Progress (%)Status
66Ongoing

Monthly Status

Background Information

Land Acquisition (Hect):(Scope:836.68/Physical progress : 831.340)=99.36% Earthwork(Lakh cum): (Scope: 266.47/Physical progress: 222.57)= 83.53% Formation (Km): (Scope: 45.887/Physical progress: 34.9)= 76.06% Major Bridge – Sub Strc. (Nos): (Scope: 27/Physical progress: 16)=59.26% Major Bridge – Sup Strc. (Nos): Scope: 27/Physical progress: 12)=44.44% Minor Bridge – Scope: 149/Physical progress: 141)=94.63% ROB (Nos): (Scope: 5/Physical progress: 4)=80% RUB (Nos): (Scope: 15/Physical progress: 14)=93.33% LHS (Nos): (Scope: 14/Physical progress: 14)=100% Tunnels (Rm): (Scope: 31169/Physical progress: 12276) = 39.39% Cut & Cover (Rm): (Scope: 1092/Physical progress: 365)=33.42% Ballast Supply (Th. Cum): (Scope: 176/Physical progress: 39)=22.16% Track Linking - Main Line (Km): (Scope: 82.5/Physical progress: 29)=35.15% Station Building (Nos.): (Scope: 8/Physical progress: 3)=37.5% Land Acquisition (Hect):(Scope:798.804 /Physical progress : 795.734)=99.61% Earthwork(Lakh cum): (Scope: 231.25/Physical progress: 203.32)= 87.92% Formation (Km): (Scope: 54.17/Physical progress: 31.550)= 58.24% Major Bridge – Sub Strc. (Nos): (Scope: 24/Physical progress: 14)=58.33% Major Bridge – Sup Strc. (Nos): Scope: 24/Physical progress: 11)=45.83% Minor Bridge – (Nos): (Scope: 156/Physical progress: 142)=91.02% ROB (Nos): (Scope: 6/Physical progress: 4)=66.66% RUB (Nos): (Scope: 15/Physical progress: 13)=86.66% LHS (Nos): (Scope: 14/Physical progress: 14)=100% Tunnels (Rm): (Scope: 30910/Physical progress: 8457) = 27.36% Cut & Cover (Rm): (Scope: 723/Physical progress: 178)=24.62% Ballast Supply (Th. Cum): (Scope: 127/Physical progress: 18)=14.17% Track Linking - Main Line (Km): (Scope: 82.5/Physical progress: 16.2)=19.64% Station Building (Nos.): (Scope: 8/Physical progress: 3)=37.5%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone