Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : NEW LINE FROM DIMAPUR TO ZUBZA(KOHIMA) NATIONAL PROJECT (NEFR).

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
6663.26663.26663.2

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4531.3879.86177.914789.15

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20260/012/2029

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
16740

Ministry Review Date

LatestLastPhysical Progress (%)Status
73Ongoing

Monthly Status

Background Information

Land Acquisition (Hect):(Scope:836.68/Physical progress : 836.68)=100% Earthwork(Lakh cum): (Scope: 266.47/Physical progress: 222.57)= 83.53% Formation (Km): (Scope: 45.887/Physical progress: 34.9)= 76.06% Major Bridge – Sub Strc. (Nos): (Scope: 28/Physical progress: 15)=53.57% Major Bridge – Sup Strc. (Nos): Scope: 28/Physical progress: 12)=42.86% Minor Bridge – Scope: 149/Physical progress: 141)=94.63% ROB (Nos): (Scope: 5/Physical progress: 4)=80% RUB (Nos): (Scope: 15/Physical progress: 14)=93.33% LHS (Nos): (Scope: 14/Physical progress: 14)=100% Tunnels (Rm): (Scope: 31328.99/Physical progress: 13178.86) = 42.07% Cut & Cover (Rm): (Scope: 1213/Physical progress: 496.8)=40.94% Ballast Supply (Th. Cum): (Scope: 132/Physical progress: 79.18)=59.98% Track Linking - Main Line (Km): (Scope: 82.5/Physical progress: 38.64)=46.84% Station Building (Nos.): (Scope: 8/Physical progress: 4)=50%Land Acquisition (Hect):(Scope:798.804 /Physical progress : 795.734)=99.61% Earthwork(Lakh cum): (Scope: 231.25/Physical progress: 203.32)= 87.92% Formation (Km): (Scope: 54.17/Physical progress: 31.550)= 58.24% Major Bridge – Sub Strc. (Nos): (Scope: 24/Physical progress: 14)=58.33% Major Bridge – Sup Strc. (Nos): Scope: 24/Physical progress: 11)=45.83% Minor Bridge – (Nos): (Scope: 156/Physical progress: 142)=91.02% ROB (Nos): (Scope: 6/Physical progress: 4)=66.66% RUB (Nos): (Scope: 15/Physical progress: 13)=86.66% LHS (Nos): (Scope: 14/Physical progress: 14)=100% Tunnels (Rm): (Scope: 30910/Physical progress: 8457) = 27.36% Cut & Cover (Rm): (Scope: 723/Physical progress: 178)=24.62% Ballast Supply (Th. Cum): (Scope: 127/Physical progress: 18)=14.17% Track Linking - Main Line (Km): (Scope: 82.5/Physical progress: 16.2)=19.64% Station Building (Nos.): (Scope: 8/Physical progress: 3)=37.5%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks