Sector Name : RAILWAYS.
Agency Name : NORTH EASTERN RAILWAY.
Project Name : CHHAPRA-BALLIA UP.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   223.39

Time Overrun (Months)-    64

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
295954954

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
783.37154.25.11942.68

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20190/05/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1290

Ministry Review Date

LatestLastPhysical Progress (%)Status
92Ongoing

Monthly Status

Background Information

TDC for commissioning of the project May - 24Sahatwar-Ballia (18 km): commissioned on 19-03-2021. Manjhi-Gautamasthan (6 km) commissioned on 17-01-2023. Sahatwar-Bakulha (25.491 km) commissioned on 28.02.2023.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks