Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EASTERN RAILWAY.
Project Name : CHHAPRA-BALLIA UP.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   254.52

Time Overrun (Months)-    83

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2959541045.82

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
942.6857.11.741001.52

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20190/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1290

Ministry Review Date

LatestLastPhysical Progress (%)Status
95.5Ongoing

Monthly Status

Background Information

TDC for commissioning of the project Dec - 24TDC for commissioning of the project May - 24

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone