Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH WESTERN RAILWAY.
Project Name : BANGURGRAM-GURIYA PATCH DOUBLING.

Reported Date : 07-OCT-21

Monthly Report : 9 / 2021

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
246.080395

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
351.2715.11.54366.92

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20190/03/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
400

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Following sections of project already commissioned : (a) Haripur-Guriya (9.00 km): •CRS inspection done on 14.04.2018. CRS has authorized the opening of section for the public carriage of passengers at a maximum permissible speed of 100 Kmphon16.04.2018. Section commissioned on 14.06.2018. (b) Sendra-Bangurgram (19.00 km):- •CRS inspection done on 25.02.2020. CRS has given authorization for provisional opening of the section for the public carriage of passengers at a maximum permissible speed of 85 kmph speed initially on DN main line& 50 kmph on UP main line from Km 350.71 to Km 355.794. Section commissioned on 25.02.2020. (c) Sendra-Haripur (19.00 km):- •CRS inspection done on 11.03.2021. CRS has given authorization for provisional opening of the section for the public carriage of passengers at a maximum permissible speed of 75 Kmph on Main line and 15 Kmph on Ponit&Crossings & loop lines. Complete project is commissioned.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks