Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : CHOTTAUDEPUR-DHAR(NL).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1793.651793.631793.63

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1615.3511.0715.421641.84

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/202612/202712/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
102.910

Ministry Review Date

LatestLastPhysical Progress (%)Status
59Ongoing

Monthly Status

Background Information

Detailed Estimate for 1347.26 Crs was sanctioned by Railway Board on 06.09.2012 for CTD-DHAR new Line 157 Kms. RB on 08.09.2021 sanctioned Electrification of project for 177.42 Crs. Part estimate for land for amounting to Rs.268.97 crore sanctioned by General Manager. Total sanctioned cost is 1793.63 Crs. Total 72.65 km commissioned up to March24. Land acquisition in process. Contracts awarded. Work is in progress in available land. Targeted section during the current year are Jobat- Dekakund (11.88 Km) & Dekakund - Tanda Road (15.70 km). Work is in progress.The detailed estimate was sanctioned in Sept 2012 at a Cost of Rs. 1347.26 Cr. MM-I for RE work was sanctioned in Jul 21 Cost Rs 177.42 Cr. Revised part Estimate for land due to escalation was sanctioned in March 2023 additional Cost of Rs 268.97 Cr. Total revised sanctioned cost of the works comes to Rs 1793.65 Cr. Chhotaudepur to Alirajpur (48 km) & Alirajpur-Khandala (9.8 km), total 57.8 km commissioned up to March23. Khandala – Jobat (14.62 Km) : CRS inspected the section on 16.05.23 and certified fit for passenger & goods opening maximum speed of 85 Kmph vide letter dt. 05.09.23. TDC : 14.62 Km - Commissioned (Khandala- Jobat) 11.88 Km - Dec23/June24 (Jobat-Dekakund) 15.70 km - Feb.24/ July24 (Dekakund - Tanda Road) 56.71 Km (Bal.) - Dec.26 (Tanda Road - Dhar) Subject to timely acquisition of land.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks