Detailed Estimate was sanctioned by railway board on 06.09.2012. Total 72.65 km commissioned up to March.24. Land acquisition in process. Contracts awarded. Work is in progress in available land. Targeted section during the current year are Jobat- Dekakund (11.88 Km) & Dekakund - Tanda Road (15.70 km). Work is in progress. | The detailed estimate was sanctioned in Sept 2012 at a Cost of Rs. 1347.26 Cr. MM-I for RE work was sanctioned in Jul 21 Cost Rs 177.42 Cr. Revised part Estimate for land due to escalation was sanctioned in March 2023 additional Cost of Rs 268.97 Cr. Total revised sanctioned cost of the works comes to Rs 1793.65 Cr.
Chhotaudepur to Alirajpur (48 km) & Alirajpur-Khandala (9.8 km), total 57.8 km commissioned up to March23. Khandala – Jobat (14.62 Km) : CRS inspected the section on 16.05.23 and certified fit for passenger & goods opening maximum speed of 85 Kmph vide letter dt. 05.09.23.
TDC : 14.62 Km - Commissioned (Khandala- Jobat)
11.88 Km - Dec23/June24 (Jobat-Dekakund)
15.70 km - Feb.24/ July24 (Dekakund - Tanda Road)
56.71 Km (Bal.) - Dec.26 (Tanda Road - Dhar)
Subject to timely acquisition of land. |