Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : AHMEDABAD-BOTAD (GC).

Reported Date : 08-MAR-22

Monthly Report : 2 / 2022

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
975.6201555.42

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1580.01168.337.11755.44

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20210/010/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Project fully commissioned on 31.10.2021 for goods traffic.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks