Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : MIYAGAM-KARJAN-DABHOI-SAMLAYA (GC).

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
844.1844.1844.1

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
593.174.451.6599.22

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/202110/202610/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
118.90

Ministry Review Date

LatestLastPhysical Progress (%)Status
41Ongoing

Monthly Status

Background Information

Work completed in Miyagaon to Dabhoi (32.31 km) and CRS inspection conducted in May,23 and section commissioned. In Dabhoi - Samalaya section ( 46.60 Km), all L sections have been approved. GADs of major bridges, designs, ESPs have been approved. GADs of minor bridges and RUBs are under approvall and will be done by june, 25.Out of total 24 villages, partial 20E of 59.51 Ha of 17 villages published on 18.10.24. and 21.03.2025. left over 20A of 15 villages will be published by 10.06.2025. 20E of all villages will likely to published 5.07.25.The project had been declared as a special Railway Project through Gazette notification dated 28.02.2023. Notification for competent authority had been issued on 07.04.2023. Contract for Relocation survey awarded on 30.05.23 and work is in progress. NOC for forest clearance tree cutting under progress. LAQ: 20A Notification issued for all villages and JM under process. (80% progress) The EPC tender can be invited only after acquisition of land. Due to delay in acquisition of land, GM has accorded approval for calling of BOQ tenders. Two BOQ tenders for Dabhoi - Waghodia & Waghodia- Samalaya has been opened on 27.07.23 and awarded on 17.11.23 & 20.11.23. Dabhoi-Wagodia (20.29 KM): Earthwork:2% work is in progress. Critical issues:- Land acquisition and transfer of Govt land Wagodia-Samlaya (26.13 KM):- Minor bridges work is in progress. Critical issues:-Land transfer from VMC in front of Theme park and other land TDC : 32.306 Km - Commissioned (Miyagam-Dabhoi) : 51.23 Km - Oct.25 (Dabhoi - Samlaya) [Phase-II Dabhoi-Wagodia (20.29 KM): -May.25, Phase-III Wagodia-Samlaya (26.13 KM):--Oct.25]

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks