Work completed in Miyagaon to Dabhoi (32.31 km) and CRS inspection conducted in May,23 and section commissioned. In Dabhoi - Samalaya section ( 46.60 Km), all L sections have been approved. GADs, designs, ESPs are under approval and will be done by April 25. Out of total 24 villages, partial 20E of 59.51 Ha of 17 villages published on 18.10.24. and21.03.2025. left over 20A of 15 villages will be published by 30.04.2025.20E of all villages will likely to published 15.05.25. | The project had been declared as a special Railway Project through Gazette notification dated 28.02.2023. Notification for competent authority had been issued on 07.04.2023. Contract for Relocation survey awarded on 30.05.23 and work is in progress. NOC for forest clearance tree cutting under progress. LAQ: 20A Notification issued for all villages and JM under process. (80% progress)
The EPC tender can be invited only after acquisition of land. Due to delay in acquisition of land, GM has accorded approval for calling of BOQ tenders. Two BOQ tenders for Dabhoi - Waghodia & Waghodia- Samalaya has been opened on 27.07.23 and awarded on 17.11.23 & 20.11.23.
Dabhoi-Wagodia (20.29 KM): Earthwork:2% work is in progress.
Critical issues:- Land acquisition and transfer of Govt land
Wagodia-Samlaya (26.13 KM):- Minor bridges work is in progress.
Critical issues:-Land transfer from VMC in front of Theme park and other land
TDC : 32.306 Km - Commissioned (Miyagam-Dabhoi)
: 51.23 Km - Oct.25 (Dabhoi - Samlaya) [Phase-II Dabhoi-Wagodia (20.29 KM): -May.25, Phase-III Wagodia-Samlaya (26.13 KM):--Oct.25] |