Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : VIRAMGAM-SAMAKHIALI (DL).

Reported Date : 28-JUN-23

Monthly Report : 6 / 2023

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1037.151491.891491.89

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1494.7245.0701539.79

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20210/03/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
200

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks