Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH CENTRAL RAILWAY.
Project Name : GWALIOR-SEOPURKALA WITH EXTENSION TO KOTA (GC).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   32.02

Time Overrun (Months)-    33

Total/Pending/Completed Milestone - 5 / 4 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2912.9603845.6

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1024.32001024.32

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20220/012/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

The Project anticipated cost is now Rs. 2912.96 crre. Present Status: Detailed estimate submitted to Rly. Board for sanction.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone