Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH WESTERN RAILWAY.
Project Name : THIYAT HAMIRA-SANU.

Reported Date : 07-OCT-21

Monthly Report : 9 / 2021

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
236.930350.45

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
273.7913.6.03287.42

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20180/01/2020

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
56.760

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Section commissioned for Goods trains on 02.01.2020.Goods train operation started on 26.08.2020.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks