Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH WESTERN RAILWAY.
Project Name : AJMER-BANGURGRAM.

Reported Date : 07-OCT-21

Monthly Report : 9 / 2021

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
213.390375

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
347.2813.76.79361.83

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20190/03/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
250

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Following sections of project already commissioned : (a) Bangurgram-Mangaliyawas (21.00km):- CRS inspection done on 13.04.2018. CRS has authorized the opening of section for the public carriage of passengers at a maximum permissible speed of 100 Kmphon16.04.2018. Section commissioned on 27.09.2018. (b) Daurai-Mangaliyawas (19.00 km):-CRS inspection done on 27/28.11.2019. CRS has authorized the opening of section for the public carriage of passengers at a maximum permissible speed of 70 Kmphinitially on 28.11.2019 and subsequently raised to 100 Kmph. Section commissioned on 28.11.2019. (c) Ajmer-Daurai (8.43 km):-CRS inspection done on 20.03.2021. CRS has authorized the opening of section for the public carriage of passengers at a maximum permissible speed of 60 Kmph on main line and 15 Kmph on new points/crossings & loop lines. with this complete section is commissioned.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks