Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH WESTERN RAILWAY.
Project Name : ALWAR-BANDIKUI DOUBLING.

Reported Date : 07-OCT-21

Monthly Report : 9 / 2021

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
242.090525

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
460.9612.92.48476.34

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20190/02/2020

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
70

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

(i)Alwar-Dhigawara (27.00km):- Section commissioned on 31.01.2019. (ii)Dhigawara-Bandikui (33.37 km):- Section commissioned on 27.02.2020.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks