Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH CENTRAL RAILWAY.
Project Name : DHOLPUR-SIRMUTTRA WITH EXTENSION TO GANGAPURCITY AND MOHARI-TANTPUR AND TANPUR-BANSI PAHARPUR.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    24324

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2030.5746.83746.83

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
22.07017.4739.54

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/012/202612/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
10545.35

Ministry Review Date

LatestLastPhysical Progress (%)Status
15Ongoing

Monthly Status

Background Information

Dholpur tehsil land paper sent to Jaipur HQ for further necessary action after site verification by state authority. Bari Tehsil land paper sent to DM office Dholpur after verification by state authority and Sirmuttra Tehsil land verification under progress.land files of 06 nos. villages has been submitted to DM/Dholpur.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone