Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : TAMLUK-BASULYA-SUTAHATA DOUBLING.

Reported Date : 17-APR-18

Monthly Report : 2 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
171.020250

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
234.996.44.33241.76

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20130/02/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
9.814.73

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Project fully completed and commissioned on 20.12.2016

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks