i) Sakri - Biraul - Harnagar (44 km) :- Commissioned .
ii) Hasanpur - Bithan (10 Km) :- Commissioned on 28.03.2023.
iii) Bithan - Kusheshwar Ashthan (14.0 Km) :- E/W - Work in progress, Minor Bridge - 06 nos completed out of 12 nos, RUB/ROB - Work in progress & Major Bridges (Substructure) - completed, Major Bridges(Superstructure) - 02 nos Completed out of 04 nos, OHE work in progress. Target month of commissioning - Oct-26
iv) Kusheshwarasthan - Harnagar (7.9 km) :-
E/W - Work in progress, Minor Br - 03 completed out of 09 no, ROB/RUB-02 completed out of 05 no (RUB 33A & 34A only box portion completed), OHE work-in progress. Target month of commissioning - Mar’ 27 | a) Hasanpur- Bithan (11 km) - Commissioned on 28.03.23
b) Bithan - Kusheswarsthan (14 km) -
E/W - Work in progress, Minor Bridge - 06 completed out of 12 no, RUB/ROB - Work in progress & Major Bridges - 6 completed out of 9, OHE work-in progress. Target month of commissioning - March-26
c) Harnagar - Kusheshwarasthan (7.9 km) -
E/W - Work in progress, Minor Br -03 completed out of 09 no, ROB/RUB-02 completed out of 05 no (RUB 33A & 34A
only box portion completed), OHE work-in progress. Target month of commissioning - Mar’27 |