a) Hasanpur- Bithan (11 km) - Commissioned on 28.03.23
b) Bithan - Kusheswarsthan (14 km) -
E/W - Work in progress, Minor Bridge - 06 completed out of 12 no, RUB/ROB - Work in progress & Major Bridges - 6 completed out of 9, OHE work-in progress. Target month of commissioning - March-26
c) Harnagar - Kusheshwarasthan (7.9 km) -
E/W - Work in progress, Minor Br -03 completed out of 09 no, ROB/RUB-02 completed out of 05 no (RUB 33A & 34A
only box portion completed), OHE work-in progress. Target month of commissioning - Mar’27 | a) Hasanpur- Bithan (11 km) -
Commissioned on 28.03.23
b) Harnagar-Kusheshwarasthan (7.9 km) -
E/W - Work in progress, Minor Br -03 completed out of 09 no, ROB/RUB-02 completed out of 05 no, OHE work-in progress. Target month of commissioning - Dec’24
c) Kusheswarsthan - Bithan (14 km) -
E/W - Work in progress, Minor Bridge - 06 completed out of 12 no, RUB/ROB - 06 completed out of 10 no & Major Bridges - 6 completed out of 9, OHE work-in progress. Target month of commissioning - Jun24
|