Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : SAKRI-HASANPUR ROAD (NL).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   126.22

Time Overrun (Months)-    24327

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
325735.2735.2

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
475.871.875.82553.49

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/03/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
750

Ministry Review Date

LatestLastPhysical Progress (%)Status
78Ongoing

Monthly Status

Background Information

a) Hasanpur- Bithan (11 km) - Commissioned on 28.03.23 b) Bithan - Kusheswarsthan (14 km) - E/W - Work in progress, Minor Bridge - 06 completed out of 12 no, RUB/ROB - Work in progress & Major Bridges - 6 completed out of 9, OHE work-in progress. Target month of commissioning - March-26 c) Harnagar - Kusheshwarasthan (7.9 km) - E/W - Work in progress, Minor Br -03 completed out of 09 no, ROB/RUB-02 completed out of 05 no (RUB 33A & 34A only box portion completed), OHE work-in progress. Target month of commissioning - Mar’27a) Hasanpur- Bithan (11 km) - Commissioned on 28.03.23 b) Harnagar-Kusheshwarasthan (7.9 km) - E/W - Work in progress, Minor Br -03 completed out of 09 no, ROB/RUB-02 completed out of 05 no, OHE work-in progress. Target month of commissioning - Dec’24 c) Kusheswarsthan - Bithan (14 km) - E/W - Work in progress, Minor Bridge - 06 completed out of 12 no, RUB/ROB - 06 completed out of 10 no & Major Bridges - 6 completed out of 9, OHE work-in progress. Target month of commissioning - Jun24

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone