Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : ARARIA-SUPAUL (NL).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    24305

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1605.171605.171605.17

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1159.86374.4579.951614.26

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/05/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
250403.81

Ministry Review Date

LatestLastPhysical Progress (%)Status
32Ongoing

Monthly Status

Background Information

a) Supaul - Pipra (21.679 Km) - Commissioned on 29 March’ 25. b) Pipra – Triveniganj (10.00 Km) - E/W & Blanketing - Work in progress, & Minor Br - Total 9 no Br. completed out of 11 no br. , RUB /LHS - completed,Balance 50.57 Acre Govt. land handing over in progress. OHE work - in progress. Target date of Commissioning - April’ 25. c) L-Section between Supaul to Araria (90 Km) has been approved and Land Boundary Pillars have been fixed. d) Soil Exploration of Major Bridges, Minor Bridges between Araria - Supaul project completed. e) Tenders for Earthwork, blanketing, minor bridges/RUB/LHS. etc and major bridges in Supaul- Pipra section has been awarded & work is in progress. f) Tender for earthwork and bridges has been awarded in Pipra - Triveniganj section & work is in progress. a) FLS completed. b) Total 1380.757 Acre Land has already been handed over to Railway by State Govt. 691.022 acre land has been handed over to Railway by DM/ Supaul. c) State Govt. has transferred Rs. 214.5 Crore to DM/Supaul for land acquisition of Araria – Supaul NL from the already deposited amount of Rs. 779.28 Crore for land acquisition of Hajipur – Sagauli NL but land not provided even after 2-3 years. d) L-Section between Supaul to Jadia (42 Km) has been approved. e) Soil Exploration of Major Bridges, Minor Bridges between Araria-Supaul project completed. f) Tenders for Earthwork, blanketing, minor bridges/RUB/LHS. etc and major bridges in Supaul- Pipra section has been awarded & work is in progress. g) Tender for earthwork and minor bridges has been awarded in Pipra- Triveniganj section & work is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone