a) Supaul - Pipra (21.679 km) :- Has been commissioned on 29 Mar 25
b) Pipra - Triveniganj (9.0 km) :- E/work - 10.955 Lcum out of 8.50 Lcum completed, Blanketing - 0.532 Lcum out of 0.45 Lcum completed, Minor Br./RUB/LHS - 14 nos Br. completed out of total 16 nos Br. OHE work is in progress. Target month of commissioning July 25
c) Araria Court to Supaul (95.0 km) :- E/work - 51.61 Lcum out of 72.27 Lcum completed, Blanketing - 1.83 Lcum out of 3.21 Lcum completed, Minor Br./RUB/LHS - 49 nos Br. completed out of total 162 nos Br. OHE work is in progress
d) L-Section between Supaul to Araria (90 Km) has been approved and Land Boundary Pillars have been fixed.
e) Soil Exploration of Major Bridges, Minor Bridges between Araria-Supaul project completed.
f) Work of fixing of Land Boundary pillar has been completed from Supaul to Araria– 95 km. | a) FLS completed.
b) Total 1380.757 Acre Land has already been handed over to Railway by State Govt. 691.022 acre land has been handed over to Railway by DM/ Supaul.
c) State Govt. has transferred Rs. 214.5 Crore to DM/Supaul for land acquisition of Araria – Supaul NL from the already deposited amount of Rs. 779.28 Crore for land acquisition of Hajipur – Sagauli NL but land not provided even after 2-3 years.
d) L-Section between Supaul to Jadia (42 Km) has been approved.
e) Soil Exploration of Major Bridges, Minor Bridges between Araria-Supaul project completed.
f) Tenders for Earthwork, blanketing, minor bridges/RUB/LHS. etc and major bridges in Supaul- Pipra section has been awarded & work is in progress.
g) Tender for earthwork and minor bridges has been awarded in Pipra- Triveniganj section & work is in progress. |