Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : ARARIA-SUPAUL (NL).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1605.171605.171605.17

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1614.2683.3252.341749.92

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20240/05/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3500

Ministry Review Date

LatestLastPhysical Progress (%)Status
65Ongoing

Monthly Status

Background Information

a) Supaul - Pipra (21.679 km) :- Has been commissioned on 29 Mar 25 b) Pipra - Triveniganj (9.0 km) :- E/work - 10.955 Lcum out of 8.50 Lcum completed, Blanketing - 0.532 Lcum out of 0.45 Lcum completed, Minor Br./RUB/LHS - 14 nos Br. completed out of total 16 nos Br. OHE work is in progress. Target month of commissioning July 25 c) Araria Court to Supaul (95.0 km) :- E/work - 51.61 Lcum out of 72.27 Lcum completed, Blanketing - 1.83 Lcum out of 3.21 Lcum completed, Minor Br./RUB/LHS - 49 nos Br. completed out of total 162 nos Br. OHE work is in progress d) L-Section between Supaul to Araria (90 Km) has been approved and Land Boundary Pillars have been fixed. e) Soil Exploration of Major Bridges, Minor Bridges between Araria-Supaul project completed. f) Work of fixing of Land Boundary pillar has been completed from Supaul to Araria– 95 km.a) FLS completed. b) Total 1380.757 Acre Land has already been handed over to Railway by State Govt. 691.022 acre land has been handed over to Railway by DM/ Supaul. c) State Govt. has transferred Rs. 214.5 Crore to DM/Supaul for land acquisition of Araria – Supaul NL from the already deposited amount of Rs. 779.28 Crore for land acquisition of Hajipur – Sagauli NL but land not provided even after 2-3 years. d) L-Section between Supaul to Jadia (42 Km) has been approved. e) Soil Exploration of Major Bridges, Minor Bridges between Araria-Supaul project completed. f) Tenders for Earthwork, blanketing, minor bridges/RUB/LHS. etc and major bridges in Supaul- Pipra section has been awarded & work is in progress. g) Tender for earthwork and minor bridges has been awarded in Pipra- Triveniganj section & work is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks