a) Supaul - Pipra (21.679 Km) - Commissioned on 29 March’ 25.
b) Pipra – Triveniganj (10.00 Km) - E/W & Blanketing - Work in progress, & Minor Br - Total 9 no Br. completed out of 11 no br. , RUB /LHS - completed,Balance 50.57 Acre Govt. land handing over in progress. OHE work - in progress. Target date of Commissioning - April’ 25.
c) L-Section between Supaul to Araria (90 Km) has been approved and Land Boundary Pillars have been fixed.
d) Soil Exploration of Major Bridges, Minor Bridges between Araria - Supaul project completed.
e) Tenders for Earthwork, blanketing, minor bridges/RUB/LHS. etc and major bridges in Supaul- Pipra section has been awarded & work is in progress.
f) Tender for earthwork and bridges has been awarded in Pipra - Triveniganj section & work is in progress. | a) FLS completed.
b) Total 1380.757 Acre Land has already been handed over to Railway by State Govt. 691.022 acre land has been handed over to Railway by DM/ Supaul.
c) State Govt. has transferred Rs. 214.5 Crore to DM/Supaul for land acquisition of Araria – Supaul NL from the already deposited amount of Rs. 779.28 Crore for land acquisition of Hajipur – Sagauli NL but land not provided even after 2-3 years.
d) L-Section between Supaul to Jadia (42 Km) has been approved.
e) Soil Exploration of Major Bridges, Minor Bridges between Araria-Supaul project completed.
f) Tenders for Earthwork, blanketing, minor bridges/RUB/LHS. etc and major bridges in Supaul- Pipra section has been awarded & work is in progress.
g) Tender for earthwork and minor bridges has been awarded in Pipra- Triveniganj section & work is in progress. |