Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : SAKRI-NIRMALI AND JHANJHARPUR-LAUKAHABAZAR AND SAHARSA-FORBESGANJ (GC).

Reported Date : 06-NOV-24

Monthly Report : 10 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
372.141470.52350

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2351.69159.1727.622538.48

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/06/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
105345

Ministry Review Date

LatestLastPhysical Progress (%)Status
97Completed

Monthly Status

Background Information

a) Jhanjharpur – Tumuria( 9 Km) - Commissioned in Mar’21 b) Raghopur – Lalitgram (20 Km) – Commissioned on 03.12.21. c) Tamuria – Nirmali (22 Km) - Commissioned in Mar’22. d) Lalitgram - Narpatganj (12 Km) - Commissioned on 13.06.22. e) Narpatganj - Forbesganj( 17 Km) - Commissioned on 11.01.23 f) Jhanjharpur - Mahrail (8.0 Km) - Commissioned in Feb’23 g) Vachaspatinagar - Khutauna (14.00 Km) - Opened for goods traffic on 30.11.23 h) Mahrail - Vachaspatinagar (13.0 km) - Commissioned on 19.01.24. i) Vachaspatinagar - Laukahabazar (23 km) - CRS inspection done on 14.03.2024 and authorization received on 28.03.2024.a) Jhanjharpur – Tumuria( 9 Km) - Commissioned in Mar’21 b) Tamuria – Nirmali (22 Km) - Commissioned in Mar’22. c) Lalitgram - Narpatganj (12 Km)- Commissioned on 13.06.22. d) Narpatganj - Forbesganj( 17 Km)- Commissioned on 11.01.23 e) Jhanjharpur - Mahrail (8.0 Km)- Commissioned in Feb’23 f) Vachaspatinagar - Khutauna (14.00 Km) - Opened for goods traffic on 30.11.23 g) Mahrail – Vachaspatinagar (13.0 Km) - Commissioned on 19.01.24. i) Khutauna - Laukahabazar (9.764 Km) - E/W & Blanketing - Work in progress, Major Bridge - completed, Minor Bridge - completed, OHE work - in progress.Target month of commissioning -April24

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks