a) Jhanjharpur – Tumuria( 9 Km) -
Commissioned in Mar’21
b) Raghopur – Lalitgram (20 Km) – Commissioned on 03.12.21.
c) Tamuria – Nirmali (22 Km) -
Commissioned in Mar’22.
d) Lalitgram - Narpatganj (12 Km) - Commissioned on 13.06.22.
e) Narpatganj - Forbesganj( 17 Km) - Commissioned on 11.01.23
f) Jhanjharpur - Mahrail (8.0 Km) -
Commissioned in Feb’23
g) Vachaspatinagar - Khutauna (14.00 Km) -
Opened for goods traffic on 30.11.23
h) Mahrail - Vachaspatinagar (13.0 km) - Commissioned on 19.01.24.
i) Vachaspatinagar - Laukahabazar (23 km) - CRS inspection done on 14.03.2024 and authorization received on 28.03.2024. | a) Jhanjharpur – Tumuria( 9 Km) -
Commissioned in Mar’21
b) Tamuria – Nirmali (22 Km) -
Commissioned in Mar’22.
c) Lalitgram - Narpatganj (12 Km)- Commissioned on 13.06.22.
d) Narpatganj - Forbesganj( 17 Km)- Commissioned on 11.01.23
e) Jhanjharpur - Mahrail (8.0 Km)-
Commissioned in Feb’23
f) Vachaspatinagar - Khutauna (14.00 Km) -
Opened for goods traffic on 30.11.23
g) Mahrail – Vachaspatinagar (13.0 Km) -
Commissioned on 19.01.24.
i) Khutauna - Laukahabazar (9.764 Km) -
E/W & Blanketing - Work in progress, Major Bridge - completed, Minor Bridge - completed, OHE work - in progress.Target month of commissioning -April24 |