Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : SAKRI-NIRMALI AND JHANJHARPUR-LAUKAHABAZAR AND SAHARSA-FORBESGANJ (GC).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   531.48

Time Overrun (Months)-    24294

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
372.141470.52350

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1952.32334.6534.512321.48

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/06/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
105345

Ministry Review Date

LatestLastPhysical Progress (%)Status
97Ongoing

Monthly Status

Background Information

a) Jhanjharpur – Tumuria( 9 Km) - Commissioned in Mar’21 b) Tamuria – Nirmali (22 Km) - Commissioned in Mar’22. c) Lalitgram - Narpatganj (12 Km)- Commissioned on 13.06.22. d) Narpatganj - Forbesganj( 17 Km)- Commissioned on 11.01.23 e) Jhanjharpur - Mahrail (8.0 Km)- Commissioned in Feb’23 f) Vachaspatinagar - Khutauna (14.00 Km) - Opened for goods traffic on 30.11.23 g) Mahrail – Vachaspatinagar (13.0 Km) - Commissioned on 19.01.24. i) Khutauna - Laukahabazar (9.764 Km) - E/W & Blanketing - Work in progress, Major Bridge - completed, Minor Bridge - completed, OHE work - in progress.Target month of commissioning -April24 a) Jhanjharpur – Tumuria( 9 Km) - Commissioned in Mar’21 b) Tamuria – Nirmali (22 Km) - Commissioned in Mar’22. c) Lalitgram - Narpatganj (12 Km)- Commissioned on 13.06.22. d) Narpatganj - Forbesganj( 17 Km)- Commissioned on 11.01.23 e) Jhanjarpur - Mahrail (8.0 Km)- Commissioned in Feb23 f) Mahrail – Chandeshwar Asthan (6.15 Km) - E/W - Work is Completed & Blanketing - in progress, Minor Bridge - Completed & Major Bridges - 02 completed out of 3 no, RUB/ROB - 04 completed out of 4 no , OHE work - in progress. Target month - Aug23 g) Chandeshwar Asthan -Vachaspatinagar (6.317 Km ) - E/W & Blanketing - Work in progress, Minor Bridge - Completed RUB/ROB - 2 completed out of 2 no , OHE work - in progress. Target month - Aug23 h) Vachaspatinagar -Khutauna (14.154 Km) - E/W & Blanketing - Work in progress, Minor Bridge - 12 completed out of 13 no Completed RUB/ROB - 7 completed out of 7 no , OHE work - in progress. Target month - Oct23 i) Khutauna -Laukahabazar (9.764 Km) - E/W - Work in progress, Major Bridge - completed, OHE work - in progress.Target month of commissioning -Jan24

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone