a) Jhanjharpur – Tumuria( 9 Km) -
Commissioned in Mar’21
b) Tamuria – Nirmali (22 Km) -
Commissioned in Mar’22.
c) Lalitgram - Narpatganj (12 Km)- Commissioned on 13.06.22.
d) Narpatganj - Forbesganj( 17 Km)- Commissioned on 11.01.23
e) Jhanjharpur - Mahrail (8.0 Km)-
Commissioned in Feb’23
f) Vachaspatinagar - Khutauna (14.00 Km) -
Opened for goods traffic on 30.11.23
g) Mahrail – Vachaspatinagar (13.0 Km) -
Commissioned on 19.01.24.
i) Khutauna - Laukahabazar (9.764 Km) -
E/W & Blanketing - Work in progress, Major Bridge - completed, Minor Bridge - completed, OHE work - in progress.Target month of commissioning -April24 | a) Jhanjharpur – Tumuria( 9 Km) -
Commissioned in Mar’21
b) Tamuria – Nirmali (22 Km) -
Commissioned in Mar’22.
c) Lalitgram - Narpatganj (12 Km)- Commissioned on 13.06.22.
d) Narpatganj - Forbesganj( 17 Km)- Commissioned on 11.01.23
e) Jhanjarpur - Mahrail (8.0 Km)-
Commissioned in Feb23
f) Mahrail – Chandeshwar Asthan (6.15 Km) -
E/W - Work is Completed & Blanketing - in progress, Minor Bridge - Completed & Major Bridges - 02 completed out of 3 no, RUB/ROB - 04 completed out of 4 no , OHE work - in progress. Target month - Aug23
g) Chandeshwar Asthan -Vachaspatinagar (6.317 Km ) -
E/W & Blanketing - Work in progress, Minor Bridge - Completed RUB/ROB - 2 completed out of 2 no , OHE work - in progress. Target month - Aug23
h) Vachaspatinagar -Khutauna (14.154 Km) -
E/W & Blanketing - Work in progress, Minor Bridge - 12 completed out of 13 no Completed RUB/ROB - 7 completed out of 7 no , OHE work - in progress. Target month - Oct23
i) Khutauna -Laukahabazar (9.764 Km) -
E/W - Work in progress, Major Bridge - completed, OHE work - in progress.Target month of commissioning -Jan24 |