Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : JAYNAGAR-BIJALPURA INCLUDING EXTENSION BIJALPURA-BARDIBAS(NEPAL) GC.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   43.03

Time Overrun (Months)-    72

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
548548783.83

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
577.26-32.950544.31

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20200/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
6012.03

Ministry Review Date

LatestLastPhysical Progress (%)Status
75Ongoing

Monthly Status

Background Information

a) Jaynagar - Kurtha (35 Km):- Commissioned. Section handed over to Govt. of Nepal on 22.10.2021. b) Kurtha to Bijalpura (17 Km):- Commissioned. Speed trial of the section has been done on 08.09.2022. Section handed over to Govt. of Nepal on 01.06.2023. c) Land between Bijalpura - Bardibas section has been acquired by Department of Railway, GON, on 07.11.2023. Survey work of Bijalpura - Bardibas section for the demarcation of the land boundary has been completed by fixing of Centerline, Boundary, and TBM Pillars.DE submitted by IRCON to Rly. Bd.,returned with observation and again submitted to Rly. Bd. after compliance, which is returned with observation. Observation complied andsubmitted to Rly. Bd. on 08.01.2025. Again after observation compliance sent to Rly. Bd. on 05.03.2025.a) Jaynagar - Kurtha (35 Km):- Commissioned. Section handed over to Govt. of Nepal on 22.10.2021. b) Kurtha to Bijalpura (18 Km):- Commissioned. Speed trial of the section has been done on 08.09.2022. Section handed over to Govt. of Nepal on 01.06.2023. c) Land between Bijalpura - Bardibas section has been acquired by Department of Railway, GON, on 07.11.2023. Survey work of Bijalpura - Bardibas section for the demarcation of the land boundary has been completed by fixing of Centerline, Boundary, and TBM Pillars.