Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : NEW BONGAIGAON-RANGIA-KAMAKGHYA DOUBLING.

Reported Date : 15-MAY-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2047.5102832.35

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3647.262.2703709.47

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20240/010/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1013.05895

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Earth Work (Lakh Cum) : (Scope=100.11/Physical Progress=95.92) = 95.81% Formation (Km) : (Scope=142.97/Physical Progress=65.72) = 45.97% Major Bridge-Sub Strc. (Nos.) : (Scope=75/Physical Progress=66) = 88% Major Bridge-Super Strc. (Nos.) : (Scope=75/Physical Progress=66) = 88% Minor Bridge(Nos.) : (Scope=38/Physical Progress=36) = 94.74% track Linking-Main Line (Km) : (Scope=142.97/Physical Progress=82.07) = 57.40% Station Building (Nos.) : (Scope=19/Physical Progress=16) = 84.21%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks