Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : NEW BONGAIGAON-RANGIA-KAMAKGHYA DOUBLING.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   13.88

Time Overrun (Months)-    62

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
179802047.51

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1702.19822.57111.552636.31

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20190/05/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
6000

Ministry Review Date

LatestLastPhysical Progress (%)Status
70Ongoing

Monthly Status

Background Information

Earth Work (Lakh Cum) : (Scope=100.11/Physical Progress=95.92) = 95.81% Formation (Km) : (Scope=142.97/Physical Progress=65.72) = 45.97% Major Bridge-Sub Strc. (Nos.) : (Scope=75/Physical Progress=66) = 88% Major Bridge-Super Strc. (Nos.) : (Scope=75/Physical Progress=66) = 88% Minor Bridge(Nos.) : (Scope=38/Physical Progress=36) = 94.74% track Linking-Main Line (Km) : (Scope=142.97/Physical Progress=82.07) = 57.40% Station Building (Nos.) : (Scope=19/Physical Progress=16) = 84.21%" Earth Work (Lakh Cum) : (Scope=100.11/Physical Progress=93.91) = 93.81% Formation (Km) : (Scope=142.97/Physical Progress=57.5) = 40.22% Major Bridge-Sub Strc. (Nos.) : (Scope=75/Physical Progress=66) = 88% Major Bridge-Super Strc. (Nos.) : (Scope=75/Physical Progress=62) = 82.67% Minor Bridge(Nos.) : (Scope=38/Physical Progress=36) = 94.74% track Linking-Main Line (Km) : (Scope=142.97/Physical Progress=67.77) = 47.4% Station Building (Nos.) : (Scope=19/Physical Progress=15) = 78.95%"

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone