Earth Work (Lakh Cum) : (Scope=100.11/Physical Progress=100.11) = 100%
Formation (Km) : (Scope=142.97/Physical Progress=142.97) = 100%
Major Bridge-Sub Strc. (Nos.) : (Scope=75/Physical Progress=75) = 100%
Major Bridge-Super Strc. (Nos.) : (Scope=75/Physical Progress=75) = 100%
Minor Bridge(Nos.) : (Scope=38/Physical Progress=38) = 100%
track Linking-Main Line (Km) : (Scope=142.97/Physical Progress=142.97) = 100%
Station Building (Nos.) : (Scope=19/Physical Progress=19) = 100%
* The track is completed & commissioned in all Block Section including RE, Minor Building works are in progress. | Earth Work (Lakh Cum) : (Scope=100.11/Physical Progress=95.92) = 95.81%
Formation (Km) : (Scope=142.97/Physical Progress=65.72) = 45.97%
Major Bridge-Sub Strc. (Nos.) : (Scope=75/Physical Progress=66) = 88%
Major Bridge-Super Strc. (Nos.) : (Scope=75/Physical Progress=66) = 88%
Minor Bridge(Nos.) : (Scope=38/Physical Progress=36) = 94.74%
track Linking-Main Line (Km) : (Scope=142.97/Physical Progress=82.07) = 57.40%
Station Building (Nos.) : (Scope=19/Physical Progress=16) = 84.21% |