Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : KURUPPANTHARA-CHINGAVANAM.

Reported Date : 14-JUL-22

Monthly Report : 6 / 2022

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
270.14457.1749.4

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
663.4529.2510.15702.85

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/03/20225/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
98Completed

Monthly Status

Background Information

Work completed and commissioned on 29.05.2022.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks