Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : CONSTRUCTION OF NL FROM KUMARGHAT-AGARTALA.

Reported Date : 13-AUG-19

Monthly Report : 6 / 2019

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
89501731.78

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1570.34-4.51.741566.57

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20070/06/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
95.65Completed

Monthly Status

Background Information

Land Acquisition (Hect.):(Scope=789.8/Physical progress=789.8)=100% Earth Work (Lakh Cum.):(Scope=347.46/Physical progress=347.46)=100% Formation (Km.):(Scope=3.2/Physical progress=3.2)=100% ROB (Nos.):(Scope=23/Physical progress=0)=0% Track Linking - Main Line (Km.):(Scope=109/Physical progress=109)=100% Track Linking - Loop & Siding Line (Km.):(Scope=8.035/Physical progress=8.035)=100% Station Building (Nos.):(Scope=6/Physical progress=6)=100% Extension of PF (km):(Scope=6.1/Physical progress=6.1)=100% Assembling & Insertion of Pts & Xing(Sets):(Scope=104/Physical progress=104)=100% Glued Joints (Nos):(Scope=652/Physical progress=652)=100%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks