Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : AGARTALA-AKHAURA NL.

Reported Date : 06-NOV-24

Monthly Report : 10 / 2024

  

   

Total/Pending/Completed Milestone - 3 / 1 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
569.630708.73

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
380.9200380.92

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20206/20229/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
10

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks