Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : AGARTALA-AKHAURA NL.

Reported Date : 09-APR-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   24.42

Time Overrun (Months)-    30

Total/Pending/Completed Milestone - 3 / 1 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
569.630708.73

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
380.9200380.92

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20206/20229/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
10

Ministry Review Date

LatestLastPhysical Progress (%)Status
84Ongoing

Monthly Status

Background Information

Electrical Sub-Station, S&T Building, all 3 Minor Bridges completed. Meter Gauge Track linking completed in Nischintpur Yard. Passenger Terminal is 98% completed. Viaduct Sub Structure: - All 1131 Piles completed, Pile Cap completed 108 Nos. out of 115 Nos. and 88 Nos out of 115 Nos pier cap completed. 3800 MT of material out of 6500, 4,700 MT of material out of 6,800 MT received at fabrication workshop. 3,800 MT Cutting work completed and fabrication work is in progress. 53 span fabrication fully completed and 35 span dispatched from the work shop. 22 spans received at site and 19 span assembly completed. 7 span Launching completed. 2 No. Span deck Slab Completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone