Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : MADURAI-BODINAYAKKANUR.

Reported Date : 28-JUN-23

Monthly Report : 6 / 2023

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
164.410592.9

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
507.7206.25513.97

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/011/202212/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1250

Ministry Review Date

LatestLastPhysical Progress (%)Status
92Completed

Monthly Status

Background Information

This project is included as GC projects planned to be commissioned by 2024 under Vision 2024 by Railway Board. Project commissioned on 08.04.2023. Part estimate for Electrification of Madurai - Bodinayakkanur section (MM) has been sanctioned by Board for Rs.98.53 cr. This work has been transferred to RE/CORE as per Board order.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks