Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : CHENGANNUR-CHINGAVANAM.

Reported Date : 13-AUG-19

Monthly Report : 6 / 2019

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
191.72369.83369.83

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
446.2-.251.08447.03

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/012/20186/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
150

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Chengannur-Tiruvalla section completed and commissioned on 03.09.2016. Tiruvalla-Changanassery section completed and commissioned on 28.03.2017. Chnganassery-Chingavanam section completed and commissioned on 22.12.2018.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks