Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : NEW BG LINE FROM BALURGHAT TO HILLY NFR.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1208.6701181.57

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
402.0310.965.8418.79

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20270/03/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
187.450

Ministry Review Date

LatestLastPhysical Progress (%)Status
8Ongoing

Monthly Status

Background Information

Earth Work (Lakh Cum.): (Scope=30/Physical progress=0.3)=1% Major Bridge - Sub Strc. (Nos.): (Scope=10/Physical progress=4)=40% Major Bridge - Sup Strc. (Nos.): (Scope=10/Physical progress=1)=10% Station Building (Nos.): (Scope=4/Physical progress=1)=25% Balurghat-Kamarpara section: Foundation work of Quarters at Balurghat in progress. Preliminary works like Site office, Field Laboratory etc. established. Earth Work (Lakh Cum.): (Scope=30/Physical progress=0.3)=1% Major Bridge - Sub Strc. (Nos.): (Scope=10/Physical progress=4)=40% Station Building (Nos.): (Scope=4/Physical progress=1)=25% Overall Progress (Physical) : 6.6%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks