Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 387.81
|
Time Overrun (Months)-
84
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Earth Work (Lakh Cum.): (Scope=30/Physical progress=0.3)=1%
Major Bridge - Sub Strc. (Nos.): (Scope=10/Physical progress=4)=43%
Station Building (Nos.): (Scope=4/Physical progress=1)=25%
EPC for Balurghat-Kamarpara section (13.787 km) will be opened on 08.01.2025.
EPC for Kamarpara-Hili section (15.187 km) will be floted in April 2025 (due to delay in LA in the section). | Earth Work (Lakh Cum.): (Scope=30/Physical progress=0.3)=1%
Major Bridge - Sub Strc. (Nos.): (Scope=10/Physical progress=4)=40%
Station Building (Nos.): (Scope=4/Physical progress=1)=25%
Overall Progress (Physical) : 6.6% |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |