Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : NEW BG LINE FROM BALURGHAT TO HILLY NFR.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   161.18

Time Overrun (Months)-    84

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
242.220632.63

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
83.29302.5.03385.82

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20200/03/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1900

Ministry Review Date

LatestLastPhysical Progress (%)Status
17Ongoing

Monthly Status

Background Information

Earth Work (Lakh Cum.): (Scope=30/Physical progress=0.3)=1% Major Bridge - Sub Strc. (Nos.): (Scope=10/Physical progress=4)=40% Station Building (Nos.): (Scope=4/Physical progress=1)=25% Overall Progress (Physical) : 6.6%Earth Work (Lakh Cum.): (Scope=30/Physical progress=0.3)=1% Major Bridge - Sub Strc. (Nos.): (Scope=10/Physical progress=4)=40% Station Building (Nos.): (Scope=4/Physical progress=1)=25% Overall Progress (Physical) : 6.6%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone