Earth Work (Lakh Cum.): (Scope=30/Physical progress=0.3)=1%
Major Bridge - Sub Strc. (Nos.): (Scope=10/Physical progress=4)=40%
Major Bridge - Sup Strc. (Nos.): (Scope=10/Physical progress=1)=10%
Station Building (Nos.): (Scope=4/Physical progress=1)=25%
Balurghat-Kamarpara section: Foundation work of Quarters at Balurghat in progress. Preliminary works like Site office, Field Laboratory etc. established. | Earth Work (Lakh Cum.): (Scope=30/Physical progress=0.3)=1%
Major Bridge - Sub Strc. (Nos.): (Scope=10/Physical progress=4)=40%
Station Building (Nos.): (Scope=4/Physical progress=1)=25%
Overall Progress (Physical) : 6.6% |